A footpath carries people, not cars, so it needs a thinner base than a driveway or patio that may take furniture and loads. This page pre-fills the paver base calculator with a 30 × 4 ft walkway (120 ft²) and 4 in of base, and compares 4 and 6 in.
| Measure | 4 in base | 6 in base |
|---|---|---|
| Base: cubic feet | 50.60 | 75.90 |
| Base: cubic yards | 1.87 | 2.81 |
| Base: cubic metres | 1.43 | 2.15 |
| Base: short tons | 2.53 | 3.80 |
| Base: tonnes | 2.30 | 3.44 |
| Bedding sand: cubic feet | 11.00 | 11.00 |
| Bedding sand: cubic yards | 0.41 | 0.41 |
| Bedding sand: short tons | 0.55 | 0.55 |
| Bedding sand: 50 lb bags | 22 | 22 |
At the default 15% compaction and 10% extra, 4 in of base over 120 ft² is 40 ft³ exact, which becomes 50.6 ft³ to buy, or 1.87 yd³.
How we got this
120 ft² × (4 ÷ 12 ft) = 40 ft³. We add the compaction allowance (loose gravel compacts to a smaller volume) and the extra percentage, then convert to cubic yards.
Things to check
- Don't over-build the base. Extra depth costs gravel and digging time without improving a light-use path. Your paver maker's guide and local conditions give the right depth.
- Soil matters more than traffic. Soft, wet clay may need more base to stay stable than sandy ground.
- Dig deep enough for everything. The hole must hold base, sand and paver thickness, so excavation depth is the sum of the three. The Project Planner adds them up.
- Count the pavers. The paver calculator gives you the count, and the 4x20 walkway page shows an example.
Estimate only. Results are approximate. Buy 5–10% extra and check quantities with your supplier before you order.
Related
Paver Base Calculator
The full calculator
- Example
Paver Base for a 12x12 Patio: How Much
Worked example
- Example
How Many Pavers for a 4x20 Walkway
Worked example
- Guide
How Deep Should Gravel Be? By Project
Depth by project, and how to turn it into yards.