Paver Base for a 4x30 Walkway: How Much?

A footpath carries people, not cars, so it needs a thinner base than a driveway or patio that may take furniture and loads. This page pre-fills the paver base calculator with a 30 × 4 ft walkway (120 ft²) and 4 in of base, and compares 4 and 6 in.

Paver Base needed for 4x30 walkway (recommended amounts, extra allowance included)
Measure4 in base6 in base
Base: cubic feet50.6075.90
Base: cubic yards1.872.81
Base: cubic metres1.432.15
Base: short tons2.533.80
Base: tonnes2.303.44
Bedding sand: cubic feet11.0011.00
Bedding sand: cubic yards0.410.41
Bedding sand: short tons0.550.55
Bedding sand: 50 lb bags2222

At the default 15% compaction and 10% extra, 4 in of base over 120 ft² is 40 ft³ exact, which becomes 50.6 ft³ to buy, or 1.87 yd³.

How we got this

120 ft² × (4 ÷ 12 ft) = 40 ft³. We add the compaction allowance (loose gravel compacts to a smaller volume) and the extra percentage, then convert to cubic yards.

Things to check

  • Don't over-build the base. Extra depth costs gravel and digging time without improving a light-use path. Your paver maker's guide and local conditions give the right depth.
  • Soil matters more than traffic. Soft, wet clay may need more base to stay stable than sandy ground.
  • Dig deep enough for everything. The hole must hold base, sand and paver thickness, so excavation depth is the sum of the three. The Project Planner adds them up.
  • Count the pavers. The paver calculator gives you the count, and the 4x20 walkway page shows an example.

Estimate only. Results are approximate. Buy 5–10% extra and check quantities with your supplier before you order.